Project Tasks

MOD-2026-359 · Internal · Current phase: Design

Progress

44%

Done

11

of 25 tasks

In Progress

2

Remaining

14

Gates

0/4

passed

!

Sales → Design Handoff

Scope calculator completed

!

Design → Production Handoff

Final design approval from client — In Progress

Production drawing package (BOM + cut lists) — Not Started

!

Production → Installation

Quality check + packaging — Not Started

Mark as Install Ready — Not Started

!

Installation → Completion

Client walkthrough + sign-off — Not Started

Completion photos + portfolio — Not Started

Sales7/7 tasks done

Initial client meeting / site visit

Amelia2026-01-16Done

Complete scope calculator

Amelia2026-01-19Done

Prepare concept proposal

Amelia2026-01-21Done

Send quotation to client

Amelia2026-01-22Done

Follow up on quotation

Amelia2026-01-27Done

Collect deposit

Amelia2026-01-28Done

Create project folder + setup

Amelia2026-01-29Done
GATE: Sales → Design HandoffBlocked: Scope calculator completed
Design4/7 tasks done

Design kickoff meeting

Adry2026-01-16Done

Site measurement / reference check

Adry2026-01-20Done

Concept design (layout + modules)

Adry2026-01-23Done

CEO design review

Jon2026-01-26Done

Client design presentation + revisions

Adry2026-02-02

OVERDUE

In Progress

Final design approval from client

Adry2026-02-04

OVERDUE

In Progress

Production drawing package (BOM + cut lists)

Adry2026-02-09

OVERDUE

Not Started
GATE: Design → Production HandoffBlocked: Final design approval from client — In Progress, Production drawing package (BOM + cut lists) — Not Started
Production0/6 tasks done

Production planning meeting

Ah Bawi2026-01-16

OVERDUE

Not Started

Material procurement + CNC programming

Ah Bawi2026-01-23

OVERDUE

Not Started

CNC cutting

Ah Bawi2026-01-28

OVERDUE

Not Started

Processing + finishing

Ah Bawi2026-02-04

OVERDUE

Not Started

Quality check + packaging

Ah Bawi2026-02-06

OVERDUE

Not Started

Mark as Install Ready

Ah Bawi2026-02-09

OVERDUE

Not Started
GATE: Production → InstallationBlocked: Quality check + packaging — Not Started, Mark as Install Ready — Not Started
Installation0/5 tasks done

Schedule installation with client

Amelia2026-01-19

OVERDUE

Not Started

Delivery to site

Ah Bawi2026-01-20

OVERDUE

Not Started

On-site installation

Ah Bawi2026-01-23

OVERDUE

Not Started

Client walkthrough + sign-off

Amelia2026-01-26

OVERDUE

Not Started

Completion photos + portfolio

Amelia2026-01-27

OVERDUE

Not Started
GATE: Installation → CompletionBlocked: Client walkthrough + sign-off — Not Started, Completion photos + portfolio — Not Started