Project Tasks

MOD-2026-010 · Yip · Current phase: Design

Progress

44%

Done

11

of 25 tasks

In Progress

2

Remaining

14

Gates

0/4

passed

!

Sales → Design Handoff

Scope calculator completed

!

Design → Production Handoff

Final design approval from client — In Progress

Production drawing package (BOM + cut lists) — Not Started

!

Production → Installation

Quality check + packaging — Not Started

Mark as Install Ready — Not Started

!

Installation → Completion

Client walkthrough + sign-off — Not Started

Completion photos + portfolio — Not Started

Sales7/7 tasks done

Initial client meeting / site visit

Amelia2025-03-21Done

Complete scope calculator

Amelia2025-03-24Done

Prepare concept proposal

Amelia2025-03-26Done

Send quotation to client

Amelia2025-03-27Done

Follow up on quotation

Amelia2025-04-01Done

Collect deposit

Amelia2025-04-02Done

Create project folder + setup

Amelia2025-04-03Done
GATE: Sales → Design HandoffBlocked: Scope calculator completed
Design4/7 tasks done

Design kickoff meeting

Irdina2025-03-21Done

Site measurement / reference check

Irdina2025-03-25Done

Concept design (layout + modules)

Irdina2025-03-28Done

CEO design review

Jon2025-03-31Done

Client design presentation + revisions

Irdina2025-04-07

OVERDUE

In Progress

Final design approval from client

Irdina2025-04-09

OVERDUE

In Progress

Production drawing package (BOM + cut lists)

Irdina2025-04-14

OVERDUE

Not Started
GATE: Design → Production HandoffBlocked: Final design approval from client — In Progress, Production drawing package (BOM + cut lists) — Not Started
Production0/6 tasks done

Production planning meeting

Ah Bawi2025-03-21

OVERDUE

Not Started

Material procurement + CNC programming

Ah Bawi2025-03-28

OVERDUE

Not Started

CNC cutting

Ah Bawi2025-04-02

OVERDUE

Not Started

Processing + finishing

Ah Bawi2025-04-09

OVERDUE

Not Started

Quality check + packaging

Ah Bawi2025-04-11

OVERDUE

Not Started

Mark as Install Ready

Ah Bawi2025-04-14

OVERDUE

Not Started
GATE: Production → InstallationBlocked: Quality check + packaging — Not Started, Mark as Install Ready — Not Started
Installation0/5 tasks done

Schedule installation with client

Amelia2025-03-24

OVERDUE

Not Started

Delivery to site

Ah Bawi2025-03-25

OVERDUE

Not Started

On-site installation

Ah Bawi2025-03-28

OVERDUE

Not Started

Client walkthrough + sign-off

Amelia2025-03-31

OVERDUE

Not Started

Completion photos + portfolio

Amelia2025-04-01

OVERDUE

Not Started
GATE: Installation → CompletionBlocked: Client walkthrough + sign-off — Not Started, Completion photos + portfolio — Not Started